Site Diary
|
Start on site |
Nov 2009 - Dec 2009 |
Site clearance, compound, Japanese Knotweed removal, pump trials, testing
|
|
Pre-excavation works |
Jan 2010 – April 2010 |
Cut-off wall/sheet piling, installation of dewatering system
|
|
Excavation & infilling |
May 2010 – Sept 2011 |
Main part of project
|
|
Decommissioning works |
Oct 2011 - Nov 2011 |
Removal of cut-off wall/sheet piling. Continuation of air quality monitoring, removal of site set-up
|